PHOTOS BY JAMM AQUINO / JAQUINO@STARADVERTISER.COM
Workers with contractor Shimmick Traylor Granite lowered a 100-foot-tall steel rebar cage as part of testing for rail construction at the Daniel K. Inouye International Airport on Friday. The test was to ensure that the soil can support the weight of the rail columns and the airport station.
Select an option below to continue reading this premium story.
Already a Honolulu Star-Advertiser subscriber? Log in now to continue reading.
Even amid all of rail’s financial uncertainty, project officials are touting the work that continues to proceed farther east toward town.
Local media members watched Friday as crews with Shimmick Traylor Granite, the contractor that’s handling the bulk of the rail work from Aloha Stadium to Middle Street, lowered a 100-foot-tall steel rebar cage down a shaft in the middle of Daniel K. Inouye
International Airport.
It was part of a test to ensure the soil there can support rail columns and the airport station as designed, explained Rusty Lucido, STG’s foundation manager. The firm expects to do at least two more such load tests this summer along that 5-mile stretch, he added.
STG secured an $875 million contract last year from the Honolulu Authority for Rapid Transportation to build rail’s elevated guideway and four stations to
Middle Street. It’s the last major contract awarded to build rail, as the city struggles to make up an approximately $3 billion deficit,
including financing, to finish the 20-mile, 21-station system all the way to Ala Moana Center.
Kiewit Infrastructure West, which is building the rail guideway from East Kapolei to Aloha Stadium, did not bid on the contract covering Aloha Stadium to Middle Street. Kiewit and HART have often clashed over change orders and unforeseen costs, and one former Kiewit consultant said last year that the firm was on course to
lose at least $100 million on the rail work.
So far STG has had no problems working with HART, STG spokeswoman Laurie Simmons said Friday. The firm is expected to be building rail to Middle Street until at least 2021.